As a project manager, you are leading a team to develop a new mobile app. Which of the following data points would be LEAST critical in making informed decisions during the project?

  • User feedback on app features and usability

  • Number of lines of code written by each developer

  • Team velocity and sprint burndown charts

  • Budget variance and cost performance index