As a project manager, you are leading a team to develop a new software application. During the planning phase, you identify that several team members lack experience with the specific programming language required for the project. What should be your next step?

  • Immediately allocate resources for a general programming training course for all team members

  • Assign tasks to the team members and expect them to learn the programming language on the job

  • Replace the team members who lack experience with the programming language

  • Assess the team's current skill levels and identify the specific training needs for the programming language