As a project manager, you have been collecting data on the progress of various project tasks. After analyzing the data, you discover that several tasks are behind schedule and over budget. What is the BEST course of action to address this situation?

  • Modify the data to show that the project is on track and within budget

  • Develop a corrective action plan to address the root causes of the delays and cost overruns

  • Ignore the data and continue with the project as planned

  • Report the findings to the project stakeholders and await further input