As a project manager, you have been informed that a key team member will be leaving the project in two weeks. What is the most effective approach to ensure knowledge transfer for project continuity?
Replace the team member with a new hire who has similar qualifications and experience
Confirm the approach for knowledge transfers with the departing team member
Discuss project responsibilities within the team to redistribute the workload
Outline expectations for the working environment to ensure a smooth transition