Free PMI Project Management Professional (PMP) Practice Question

As a project manager, you have conducted a training session for your team on a new software tool that will be used in the upcoming project. Which of the following is the most effective way to measure the training outcomes?

  • Ask team members to provide verbal feedback on their confidence in using the software tool

  • Conduct a practical assessment that requires team members to demonstrate their proficiency in using the software tool

  • Rely on team members' self-assessment of their ability to use the software tool effectively

  • Conduct a written test to assess the team's understanding of the software tool