As a project manager, you have identified a stakeholder who has high influence over project outcomes but low interest in the day-to-day operations of the project. Which of the following actions would be most appropriate to manage this stakeholder?
Exclude them from communications and updates, as they do not have a high interest in the project
Keep them informed through periodic high-level updates about project progress
Involve them in the decision-making process for day-to-day operations of the project
Provide them with frequent, detailed communications to ensure they are fully informed