Free PMI Project Management Professional (PMP) Practice Question

As a project manager, you have identified a stakeholder who has high influence over project outcomes but low interest in the day-to-day operations of the project. Which of the following actions would be most appropriate to manage this stakeholder?

  • Exclude them from communications and updates, as they do not have a high interest in the project

  • Keep them informed through periodic high-level updates about project progress

  • Involve them in the decision-making process for day-to-day operations of the project

  • Provide them with frequent, detailed communications to ensure they are fully informed

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.