As a project manager, you have identified several impediments affecting your team's performance. Which of the following factors should be considered first when prioritizing these issues?

  • The availability of resources to tackle the impediment

  • The complexity of the solution required to address the impediment

  • The effect of the impediment on team morale

  • The impact of the impediment on project objectives