Free PMI Project Management Professional (PMP) Practice Question

As part of supporting organizational change, what is a crucial analysis a project manager must perform to adapt the project plan to ongoing transformation within the company?

  • Postpone all project timelines until organizational changes settle

  • Request additional funding to shield the project from any organizational changes

  • Conduct an impact analysis to identify organizational change repercussions on the project

  • Transfer project leadership to the organizational change management team

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment