Free PMI Project Management Professional (PMP) Practice Question

As the project manager, you are about to embark on a new project. In order to formally authorize the project and establish your authority as a project manager to apply resources to the project activities, you need to create a key document. Which of the following options BEST represents this document?

  • Project Charter

  • Project Management Plan

  • Work Breakdown Structure

  • Stakeholder Register