As the project manager, you have identified a potential change that could significantly improve the project outcome. What should be your first step in managing this change?
Execute the change management process according to the project guidelines
Determine the strategy to handle the change, considering its impact and alignment with project goals
Determine a change response to move the project forward and inform consulting stakeholders
Embrace the need for change without assessing its potential impact on the project