Free PMI Project Management Professional (PMP) Practice Question

As the project manager, you have identified a potential change that could significantly improve the project outcome. What should be your first step in managing this change?

  • Execute the change management process according to the project guidelines

  • Determine the strategy to handle the change, considering its impact and alignment with project goals

  • Determine a change response to move the project forward and inform consulting stakeholders

  • Embrace the need for change without assessing its potential impact on the project

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.