During a project status meeting, you observe a heated discussion between two team members, Alex and Sam. Alex expresses disappointment in Sam's recent design decisions, stating that they deviate from the original project vision. Sam counters by emphasizing the need for flexibility and adaptation to stakeholder feedback. As the project manager, you sense that this disagreement may have deeper roots. What is the most likely stage of this conflict?

  • Escalation

  • Latent

  • Felt

  • Perceived