During a project update meeting, the project manager notices a gap in understanding between what was agreed upon for the project’s next steps and the team members' current perceptions. Which action is BEST suited to address and clarify this discrepancy?

  • Organize a dedicated meeting to specifically discuss and clarify the misunderstanding.

  • Continue with the project as planned without addressing the misunderstanding.

  • Send a detailed email to all team members repeating the information.

  • Assume that the misunderstanding will resolve itself over time.