Free PMI Project Management Professional (PMP) Practice Question

During a project update meeting, the project manager notices a gap in understanding between what was agreed upon for the project’s next steps and the team members' current perceptions. Which action is BEST suited to address and clarify this discrepancy?

  • Assume that the misunderstanding will resolve itself over time.

  • Organize a dedicated meeting to specifically discuss and clarify the misunderstanding.

  • Send a detailed email to all team members repeating the information.

  • Continue with the project as planned without addressing the misunderstanding.

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.