During a qualitative risk analysis meeting, the project manager organizes a risk workshop with key project stakeholders. What is the PRIMARY purpose of conducting a risk workshop?
To create a detailed project schedule including all identified risks and their corresponding response actions
To assign budget allocations to each identified risk based on cost impact
To transfer ownership of project risks to the stakeholders attending the workshop
To develop an initial understanding of each identified risk's probability, impact, and determine appropriate prioritization for further analysis or action