Free PMI Project Management Professional (PMP) Practice Question

During a software development project, the project manager decides to adopt an iterative approach to incorporate lessons learned into the project life cycle. After each development sprint, which of the following activities should primarily be conducted to best utilize the iterative, incremental practices?

  • Updating the risk management plan to include new potential risks

  • Holding a retrospective meeting to discuss the outcomes of the sprint and areas for improvement

  • Revising the project's communication plan to include additional stakeholders

  • Conducting a mid-project external audit to assess compliance with industry standards

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.