During an agile project's retrospective, the team has identified several possible improvements for their process. Which of the following actions would BEST align with the agile principle of continuous improvement?

  • The team prioritizes improvements that have the longest tradition in the company, respecting the established practices.

  • The Product Owner chooses the most critical improvements.

  • The team selects only a few improvements to focus on based on the team's capacity to address in the next iteration, planning to measure the outcomes for validation.

  • The team implements all identified improvements at once to maximize the chances of process enhancement.