Free PMI Project Management Professional (PMP) Practice Question

During the execution of a project, what is the BEST approach to ensure that the project continues to align with the desired business value?

  • Increase the frequency of project status reports to the executive team to every week instead of every month.

  • Convene a monthly meeting with stakeholders to review the project's progress against its original financial projections.

  • Assign a dedicated team to monitor competitive activities and adjust the project scope accordingly without consulting stakeholders.

  • Regularly review the project objectives and deliverables in response to both updated market conditions and stakeholder inputs.