During the execution phase of a project, a key stakeholder requests a significant change in the project scope. As the project manager, what should be your immediate course of action?
Reject the change request to avoid any disruptions to the project plan
Immediately implement the change to satisfy the key stakeholder
Assess the impact of the requested change on the project's objectives, timeline, and budget