During the execution phase of a project, a new government regulation is announced that impacts the materials used in the project's product. What is the FIRST action a project manager should take to address the change in the project's external business environment?
Assess the impact of the new regulation on the project scope/backlog
Request additional funds to cover potential costs associated with the regulation
Revise the project schedule and budget
Inform all stakeholders about the new regulation