Free PMI Project Management Professional (PMP) Practice Question

During the execution phase of a project, the project manager has identified a new risk that threatens to delay the project deliverables. What should be the project manager's next step after identifying and documenting the risk?

  • Wait until the risk becomes an issue before formulating a response.

  • Assess the impact and likelihood of the risk to prioritize it appropriately.

  • Communicate the risk to all stakeholders to keep them informed.

  • Develop mitigation strategies to address the identified risk.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.