During the execution phase of a project, the project manager recognizes valuable insights that could enhance the performance of the current project as well as future projects. What is the BEST approach to ensure that this knowledge is captured and used effectively?

  • Document the insights in the lessons learned register and ensure they are reviewed and accessible for future projects

  • Discuss the insights in team meetings without formally recording them until the end of the project

  • Wait until the project closure to record all insights and learnings

  • Email a summary of insights to all stakeholders at the end of the project