During the execution phase of a project, what is the primary objective of performing a risk reassessment?
To establish a list of primary risks to be addressed during the remainder of the project.
To conclude risk management activities by confirming that initial risk responses are permanently fixed
To document risk mitigation actions in a plan and assign risk oversight to a designated manager.
To conclude risk management activities by confirming the effectiveness of initial risk responses.