Free PMI Project Management Professional (PMP) Practice Question

During the execution phase of a project, what is the primary objective of performing a risk reassessment?

  • To establish a list of primary risks to be addressed during the remainder of the project.

  • To conclude risk management activities by confirming that initial risk responses are permanently fixed

  • To document risk mitigation actions in a plan and assign risk oversight to a designated manager.

  • To conclude risk management activities by confirming the effectiveness of initial risk responses.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.