Free PMI Project Management Professional (PMP) Practice Question

During the execution phase of a project, which of the following would BEST represent a potential threat to maintaining compliance with health and safety regulations?

  • Budget cuts that force a reduction in project expenditures

  • Planning for upcoming organizational changes

  • Changes in project resource allocation that result in a shortage of personnel with health and safety management expertise

  • An organizational restructure that does not affect the project team composition

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment