During the execution phase of a project, you discover that a critical piece of equipment has malfunctioned, causing a two-week delay in the critical path activities. Which of the following actions should you take to best address this issue and keep the project on track?

  • Expedite the repair or replacement of the critical piece of equipment and reassign resources to parallel tasks not on the critical path.

  • Request additional resources to make up for lost time once the equipment is repaired or replaced.

  • Submit a change request to extend the project deadline to accommodate the two-week delay.

  • Wait to discuss the equipment malfunction at the next monthly steering committee meeting to decide on actions.