Free PMI Project Management Professional (PMP) Practice Question

During the execution phase of a project, you notice that the current supplier's delivery timelines are regularly falling short of the agreed-upon schedule stipulated in the contract. This is beginning to impact the project's critical path. As a PMP certified project manager, what should be your best course of action?

  • Meet with the supplier to discuss the performance issues and identify improvement plans.

  • Accept the delays as part of the project's risk and adjust the project schedule accordingly.

  • Send a formal notice to the supplier stressing the contract's enforceability to ensure adherence to delivery schedules.

  • Terminate the current contract immediately and find a new supplier to work with.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.