During the execution phase of a software development project, your team encounters several impediments: a critical software tool license has expired, there is a miscommunication between the development and design teams leading to delays, and there is a sudden unavailability of a key team member due to health reasons. As the project manager, which of these should you prioritize to address first?

  • Renew the expired software tool license.

  • Resolve the miscommunication between the teams.

  • Request an external consultant to assess all issues.

  • Address the unavailability of the key team member.