Free PMI Project Management Professional (PMP) Practice Question

During the initial phase of a new construction project, you have identified a list of stakeholders that includes the client, the local government authorities, the project team, and the residents of the nearby community. Based on their level of interest and ability to impact the project, which of the following is the most appropriate way to categorize the local government authorities?

  • Low power, low interest stakeholders, because their influence and interest in the project are minimal.

  • Low power, high interest stakeholders, because while they have an interest in the project's success, they can't significantly influence outcomes.

  • High power, high interest stakeholders, because they can influence project outcomes and are interested in the project's success.

  • High power, low interest stakeholders, because although they can impact the project, they generally have a low interest in the day-to-day progress.