During the negotiation process, which of the following is the most effective approach to verify that the objectives of the project agreement are met?
Discuss the agreement with the project sponsor and key stakeholders
Assess the feasibility of the project objectives based on available resources and constraints
Review the project charter, scope statement, and other relevant project documents
Analyze the potential risks associated with the project objectives and develop mitigation strategies