During the planning phase of a project, the project manager is determining the levels of uncertainty the organization is willing to accept in relation to the project's objectives. What is this an example of?
Establishing risk appetite and thresholds
Conducting a SWOT analysis
Performing qualitative risk analysis
Developing a risk management plan