During the process of sequencing activities for a construction project, the project manager has identified dependencies that are based on known best practices within the building industry. These dependencies are commonly referred to as:

  • External Dependencies

  • Internal Dependencies

  • Discretionary Dependencies

  • Mandatory Dependencies