During the procurement planning stage of a Waterfall project, which aspect is most critical for the project manager to align with the organization's financial systems and legal requirements?
Focusing exclusively on the speed of procurement processes to accelerate project delivery.
Assessing only the technical capabilities of potential sellers to ascertain their fit for the project.
Prioritizing procurement activities based solely on the availability of procurement resources.
Identifying procurement strategy aspects such as project delivery methods, contract types, and procurement phases.