During the project closure or transition phase, which of the following is the most important factor to consider when validating readiness for transition?

  • Confirming that all deliverables meet the established acceptance criteria

  • Ensuring that resources are allocated for the next phase or project

  • Obtaining stakeholder approval for the transition plan

  • Verifying that all project team members have transferred their knowledge to the operations team