During the quantitative risk analysis phase, what does a Decision Tree Analysis primarily help to determine?
It identifies the sequence of scheduled activities in the critical path method.
It calculates the Expected Monetary Values (EMVs) for different possible scenarios assisting in choosing the optimal decision path.
It indicates the interdependencies of project tasks within a Work Breakdown Structure (WBS).
It determines the degree of consensus achieved in a Delphi Technique.