Free PMI Project Management Professional (PMP) Practice Question

During the quantitative risk analysis phase, what does a Decision Tree Analysis primarily help to determine?

  • It identifies the sequence of scheduled activities in the critical path method.

  • It calculates the Expected Monetary Values (EMVs) for different possible scenarios assisting in choosing the optimal decision path.

  • It indicates the interdependencies of project tasks within a Work Breakdown Structure (WBS).

  • It determines the degree of consensus achieved in a Delphi Technique.

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.