Given a project with the following activities and durations:

  • Activity A (Duration: 3 days, depends on no other activity)
  • Activity B (Duration: 5 days, depends on Activity A)
  • Activity C (Duration: 2 days, depends on Activity A)
  • Activity D (Duration: 4 days, depends on Activity B and Activity C)

What is the Early Finish (EF) for Activity D?

  • 12 days

  • 11 days

  • 8 days

  • 9 days