Free PMI Project Management Professional (PMP) Practice Question

Given that an agile project is underway and a sprint is in progress, what is the most effective action for a team to take if key stakeholders introduce new requirements that might affect the current sprint goals?

  • Ignore new requirements until the current project phase is complete to avoid disruptions.

  • Record the new requirements in the product backlog for prioritization and planning in subsequent sprints.

  • Halt the current sprint and start planning a new sprint to incorporate the new requirements.

  • Continue with the sprint without acknowledging the new requirements to maintain the sprint's velocity.

This question's topic:
PMI Project Management Professional (PMP) / 
Agile
Your Score:

Check or uncheck an objective to set which questions you will receive.