Free PMI Project Management Professional (PMP) Practice Question

If a project manager, while in the process of executing the project, realizes the team lacks a particular expertise required to complete an upcoming activity effectively, which of the following would be the BEST initial action in accordance with good practice within Project Resource Management?

  • Delay the activity until the next project phase while seeking an expert to join the project team.

  • Inform the project sponsor about the lack of expertise and request a decision on how to proceed.

  • Proceed with the activity using current team members and capitalize on their ability to learn the necessary skills quickly during the execution of the activity.

  • Review the resource management plan for guidance on addressing the expertise gap and consider options such as training, hiring, or subcontracting to acquire the necessary expertise.

This question's topic:
PMI Project Management Professional (PMP) / 
Waterfall
Your Score:

Check or uncheck an objective to set which questions you will receive.