Free PMI Project Management Professional (PMP) Practice Question

If a project's Earned Value (EV) is reported as $750,000 and the Actual Cost (AC) incurred is $800,000, what is the Cost Variance (CV) for the project?

  • -$25,000

  • $50,000

  • $750,000

  • -$50,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.