Free PMI Project Management Professional (PMP) Practice Question
If a project's Earned Value (EV) is reported as $750,000 and the Actual Cost (AC) incurred is $800,000, what is the Cost Variance (CV) for the project?
Cost Variance (CV) is calculated as CV = EV - AC. If the Earned Value (EV) is $750,000 and the Actual Cost (AC) is $800,000, then the Cost Variance (CV) would be $750,000 - $800,000, which equals -$50,000. This negative CV indicates that the project is over budget, as the costs incurred to achieve the earned value are higher than the value of the work performed.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What does Earned Value (EV) represent in project management?
What does Actual Cost (AC) mean in the context of project management?
Why is Cost Variance (CV) important in project management?
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features