The Late Finish (LF) day is calculated by adding the Duration to the Late Start (LS) and then subtracting 1 to account for the fact that the Late Start is the first day of the activity.
Formula: LF = LS + Duration - 1
Inputs:
Late Start (LS) = 5
Duration = 7
Calculation: LF = 5 + 7 - 1 = 11
The Late Finish (LF) day is day 11.