Free PMI Project Management Professional (PMP) Practice Question
In a network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 12. What is the Early Start (ES) for Activity B?
The correct answer is 12. The Early Start (ES) of an activity is determined by the latest Early Finish (EF) of its predecessors. In this case, Activity B has two predecessors: Activity A with an EF of 10, and Activity C with an EF of 12. Since we need to wait for both predecessors to finish before starting Activity B, we must use the later of the two EF values, which is 12. This ensures that all predecessor activities are completed before Activity B can begin. It's important to note that we don't add these values or use the earlier EF, as either approach would lead to an incorrect schedule.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What does Early Finish (EF) mean in project management?
How do you calculate Early Start (ES) and Early Finish (EF)?
Why is it important to identify the latest EF in determining the ES for subsequent activities?