Free PMI Project Management Professional (PMP) Practice Question

In a network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 12. What is the Early Start (ES) for Activity B?

  • 11

  • 12

  • 10

  • 22

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.