Free PMI Project Management Professional (PMP) Practice Question

In PERT estimation, if an activity has an optimistic duration of 3 days, a most likely duration of 5 days, and a pessimistic duration of 13 days, the Expected Duration (TE) is 6 days.

  • False

  • True

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.