Free PMI Project Management Professional (PMP) Practice Question
In PERT estimation, if an activity has an optimistic duration of 3 days, a most likely duration of 5 days, and a pessimistic duration of 13 days, the Expected Duration (TE) is 6 days.
In PERT estimation, the expected duration (TE) is calculated by taking an average of three estimates: the optimistic, the most likely, and the pessimistic. The most likely duration gets more weight because it's the most probable.
Here’s how it works:
Take the optimistic duration (3 days).
Multiply the most likely duration (5 days) by 4, because it's considered more reliable.
Then, add the pessimistic duration (13 days).
Add them all together: 3 + 4(5) + 13 = 36.
Divide the total by 6: 36 ÷ 6 = 6 days.
So, the expected duration (TE) is 6 days. This method balances all the estimates while giving more weight to the most likely one.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does PERT stand for in project management?
Open an interactive chat with Bash
Can you explain how the PERT formula is derived?
Open an interactive chat with Bash
Why are durations rounded to two decimal places in project management?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features