In response to emerging economic sanctions affecting critical project resources, what should the project manager principally focus on to maintain the project's objectives?

  • Increase communication with stakeholders

  • Evaluate and update the project scope to reflect the impact of the sanctions

  • Terminate the project immediately to avoid risks associated with the sanctions

  • Proceed with the project as planned to maintain the project schedule

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment