Free PMI Project Management Professional (PMP) Practice Question

In the context of a Waterfall project, you are assessing the stakeholder engagement level and realize it differs from the desired state outlined in your engagement plan. What should be your BEST course of action?

  • Focus on stakeholders who are supportive and maintain current engagements with others

  • Send out a general survey to all stakeholders to ask for their current satisfaction levels and general feedback

  • Increase the frequency of stakeholder meetings of each stakeholder's specific engagement level

  • Perform a root cause analysis to identify underlying issues with stakeholder engagement and adjust your strategies accordingly

This question's topic:
PMI Project Management Professional (PMP) / 
Waterfall
Your Score:

Check or uncheck an objective to set which questions you will receive.