In the context of creating a Work Breakdown Structure (WBS), which of the following best illustrates the concept of decomposition?
Dividing project deliverables into smaller tasks until they can be adequately managed and assigned
Assigning financial reserves to account for uncertainty in project costs
Assigning responsibilities and accountability for individual project deliverables
Drafting the project schedule with milestones for deliverables completion as a breakdown or burndown chart