Free PMI Project Management Professional (PMP) Practice Question

In the context of project management, which process ensures that risk management is systematically executed throughout the project's life cycle, beginning with initial planning and continuing through project execution?

  • Integration of Risk Management

  • Project Communications Management

  • Risk Register Updates

  • Risk Urgency Assessment