Free PMI Project Management Professional (PMP) Practice Question

In the middle of a major infrastructure project, it's discovered that recent industry-wide safety regulations have been updated, but the current project safety protocols do not reflect these changes. What should be the project manager's initial response to ensure the project aligns with these updated regulations?

  • Implement immediate trainings for the construction team on best safety practices.

  • Schedule an emergency meeting with the team to remind them about the importance of safety on-site.

  • Order the latest safety gear touted as the industry best

  • Review and realign the project's safety protocols to meet the newly introduced safety standards.