Free PMI Project Management Professional (PMP) Practice Question

On a construction project, if the Late Start (LS) for the installation of fixtures is scheduled for day 25 and is expected to take 10 days, what is the Late Finish (LF) for this activity?

  • Day 35

  • Day 24

  • Day 34

  • Day 36

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.