Free PMI Project Management Professional (PMP) Practice Question
On a construction project, if the Late Start (LS) for the installation of fixtures is scheduled for day 25 and is expected to take 10 days, what is the Late Finish (LF) for this activity?
Late Finish (LF) is calculated by adding the duration of the activity to the Late Start (LS). With a Late Start (LS) on day 25 and an installation activity duration of 10 days, the Late Finish (LF) would be: LF = LS + Duration, which results in LF = 25 + 10, so LF is day 35.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the significance of Late Start (LS) in project scheduling?
Open an interactive chat with Bash
Can you explain how to calculate Late Finish (LF) for other project activities?
Open an interactive chat with Bash
What is the difference between Late Finish (LF) and Early Finish (EF)?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features