On a construction project, if the Late Start (LS) for the installation of fixtures is scheduled for day 25 and is expected to take 10 days, what is the Late Finish (LF) for this activity?
Late Finish (LF) is calculated by adding the duration of the activity to the Late Start (LS). With a Late Start (LS) on day 25 and an installation activity duration of 10 days, the Late Finish (LF) would be: LF = LS + Duration, which results in LF = 25 + 10, so LF is day 35.