On a project with a Budget at Completion (BAC) of $1,200,000, the Planned Value (PV) at a given milestone was expected to be $500,000. However, at that point, the Earned Value (EV) was actually $450,000. What is the Schedule Variance (SV) at this milestone?
$50,000
-$100,000
0
-$50,000