Free PMI Project Management Professional (PMP) Practice Question

On a project with a Budget at Completion (BAC) of $1,200,000, the Planned Value (PV) at a given milestone was expected to be $500,000. However, at that point, the Earned Value (EV) was actually $450,000. What is the Schedule Variance (SV) at this milestone?

  • $50,000

  • -$100,000

  • 0

  • -$50,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.