Free PMI Project Management Professional (PMP) Practice Question

On a project with a Budget at Completion (BAC) of $500,000, the project team has planned to complete 45% of the work by the end of the third month. What is the Planned Value (PV) at the end of the third month?

  • $200,000

  • $225,000

  • $275,000

  • $250,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.