Free PMI Project Management Professional (PMP) Practice Question
On a project with a Budget at Completion (BAC) of $500,000, the project team has planned to complete 45% of the work by the end of the third month. What is the Planned Value (PV) at the end of the third month?
Planned Value (PV) is calculated by multiplying the Planned Percentage Complete by the Budget at Completion (BAC). In this scenario, with a BAC of $500,000 and 45% of the work planned to be completed, the PV is 0.45 (or 45%) of $500,000, which equals $225,000. This means by the end of the third month, the project planned to have $225,000 worth of work completed.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What is Budget at Completion (BAC)?
How is Planned Value (PV) used in project management?
What does the Planned Percentage Complete indicate?
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features