Resource leveling always maintains the original project completion date.
False
True
The correct answer is False. Resource leveling is a technique used to resolve resource conflicts or overallocation by adjusting the project schedule. While it aims to balance the demand for resources with the available supply, it often results in extending the project timeline.
Unlike resource smoothing, which maintains the project's critical path and completion date, resource leveling may impact the project schedule by extending the duration. This is because resource leveling focuses on resolving overallocation issues, even if it means delaying certain tasks or extending the overall project timeline.
It's important for project managers to understand that while resource leveling can effectively address resource conflicts, it may come at the cost of a longer project duration. This trade-off between resource optimization and schedule adherence is a key consideration in project management decision-making.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features