Resource smoothing can extend the project's critical path.
True
False
The correct answer is False. Resource smoothing is a technique used to adjust the start and finish dates of activities within their available float to create a more balanced resource usage profile. Importantly, resource smoothing does not change the project's critical path or overall duration.
Unlike resource leveling, which can extend the project timeline, resource smoothing works within the existing schedule constraints. It aims to reduce peaks and valleys in resource utilization without impacting the project's completion date or critical path.
This characteristic of resource smoothing is what distinguishes it from other resource optimization techniques. Project managers use resource smoothing when they need to balance resource usage while still maintaining the original project schedule and critical path.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features