This statement is true. Resource smoothing is a resource optimization technique used in project management to adjust the timing of activities within their available float without affecting the project's critical path or overall duration. It aims to create a more balanced resource usage profile throughout the project.
Unlike resource leveling, which may extend the project schedule, resource smoothing works within the existing project timeline. It focuses on utilizing the available float of non-critical activities to resolve resource conflicts or overallocation issues. This technique helps project managers to efficiently allocate resources while maintaining the original project end date.
It's important to note that resource smoothing may not resolve all resource conflicts, especially in projects with limited float or highly constrained resources. In such cases, other resource management techniques or schedule adjustments might be necessary.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What is resource leveling and how is it different from resource smoothing?
What is the critical path in project management?
What is float in project management?
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features